Ore Reserve Quadruples for Rhyolite Ridge Project; Reaffirms Robust Project Economics

Ioneer Ltd (ASX: INR, Nasdaq: IONR) (Ioneer) is pleased to announce a 308% upgrade to the Ore Reserve estimate for its 100%-owned Rhyolite Ridge Lithium-Boron Project (‘Rhyolite Ridge’ or the ‘Project’) in Nevada, USA, alongside updated Project economics.

  • Rhyolite Ridge Ore Reserve more than quadrupled from 60 million tonnes in 2020 to 247 million tonnes, delivering a mine life of 95 years
  • Ore Reserve now contains a total of 1.92 Mt of lithium carbonate equivalent and 7.68 Mt of boric acid equivalent
  • Underpinning plans for a large, long-life, low-cost expandable operation, producing lithium carbonate, boric acid and then battery-grade lithium hydroxide
  • Stable co-product – boric acid accounts for an average 25% of annual revenue in the first 25 years; helping ensure positive EBITDA at low lithium prices and EBITDA margin of 65.7% based on average production over first 25 years
  • All-in sustaining cash cost of US$5,745 per metric tonne lithium carbonate equivalent places the Rhyolite Ridge Project in the bottom of the global lithium cost curve
  • Compelling Project economics with an after-tax NPV of US$1.367 billion, and an unlevered, after-tax internal rate of return (IRR) of 14.5%

The Ore Reserve has increased by 186.6 million tonnes (Mt) and approximately 48% of the Mineral Resource has been converted into Reserve, now estimated at:

  • 246.6 Mt at 1,464 ppm lithium and 5,444 ppm boron
  • Containing 1.92 Mt of Lithium Carbonate Equivalent (LCE) and 7.68 Mt of Boric Acid Equivalent (BAE)

“Today’s updated Reserve and Mine Plan reinforces the importance of Rhyolite Ridge’s remarkable mineralogy. Our Ore Reserve estimate of 247 Mt containing a total of 1.92 Mt LCE and 7.68 Mt BAE make it the largest lithium-boron Reserve in the world,” said Bernard Rowe, Managing Director, Ioneer. “It allows Ioneer to match prevailing market conditions and blend or prioritise ore to produce a valuable boric acid co- product, whose market is uncorrelated with the Project’s primary lithium product. No other lithium project offers this level of flexibility and economic advantage. In periods of low cycle lithium pricing, like today, we plan to prioritize the high-boron ore production to optimize the relative proportion of total revenue derived from boric acid.”

By prioritising High-Boron (Hi-B) ore in the first 25 years of production, the Project is poised to produce an average of ~19,200 tonnes per annum (tpa) of LCE, and 116,400 tpa of boric acid (see Table 1).

The updated Ore Reserve estimate, 95-year mine plan for stage one operations, and Project economics reaffirms Rhyolite Ridge as a highly attractive global Project to produce lithium carbonate, lithium hydroxide and boric acid. The updated findings position Ioneer, on an LCE basis, in the lowest cost quartile for lithium production globally with an estimated all-in sustaining cash cost to produce battery grade lithium hydroxide of US$5,745 and a cash cost of C1 $3,858 per tonne net of expected boric acid revenue in the first 25 years.

The Project has a stable overall operating cost structure to produce lithium carbonate and battery grade lithium hydroxide due to the scale and reliability of its boric acid credit. Boron remains one of the most stable natural resource commodities over many decades.

Ioneer has refined Project plans over the past four years and updates now include an Association for the Advancement of Cost Engineering (AACE) Class 2 capital cost estimate (-10%, +15%) with approximately 70% of the Project’s engineering complete. As a result of this and other engineering work including RAM analysis and detailed engineering design, Ioneer has adopted a more conservative approach to plant availability, equipment downtime and maintenance strategies. While this approach reduces bottom line economics, the Company believes it is appropriate for a Project of this type and scale.

The Company now estimates total capital expenditure to complete the Project will be US$1,667.9 million, including a 10% contingency.

Click here for the full ASX Release

This post appeared first on investingnews.com

Become a VIP member by signing up for our newsletter. Enjoy exclusive content, early access to sales, and special offers just for you! As a VIP, you'll receive personalized updates, loyalty rewards, and invitations to private events. Elevate your experience and join our exclusive community today!



    By opting in you agree to receive emails from us and our affiliates. Your information is secure and your privacy is protected.

    You May Also Like

    Latest News

    Sister Stephanie Schmidt had a hunch about what her fellow nuns would discuss over dinner at their Erie, Pennsylvania, monastery on Wednesday night. The...

    Latest News

    In the final three weeks of the presidential race, former president Donald Trump and his advisers have attacked one particular foe more than three...

    Latest News

    “And there’s very few states that benefit like you do from fracking. I mean, you have 500,000 jobs.” — Former president Donald Trump, remarks...

    Latest News

    A former deputy Palm Beach County sheriff who fled to Moscow and became one of the Kremlin’s most prolific propagandists is working directly with...

    Disclaimer: Deluxeinvestmentgroup.com, its managers, its employees, and assigns (collectively “The Company”) do not make any guarantee or warranty about what is advertised above. Information provided by this website is for research purposes only and should not be considered as personalized financial advice. The Company is not affiliated with, nor does it receive compensation from, any specific security. The Company is not registered or licensed by any governing body in any jurisdiction to give investing advice or provide investment recommendation. Any investments recommended here should be taken into consideration only after consulting with your investment advisor and after reviewing the prospectus or financial statements of the company.


    Copyright © 2025 deluxeinvestmentgroup.com